Hammered
NAXJA Forum User
- Location
- Jeep Fiend Club
I found one post that steers me in the right direction....
Any guys here that have done this PLEASE tell me the steps you took to do it correctly.
Stainless (High in nickel) wire??
Preheat the weld area??
Drain the axle??
Remove Shafts???
I read this, which is good info. I want to know more. :skull1:
Any guys here that have done this PLEASE tell me the steps you took to do it correctly.
Stainless (High in nickel) wire??
Preheat the weld area??
Drain the axle??
Remove Shafts???
I read this, which is good info. I want to know more. :skull1:
BRIANHO13 said:I had a fab shop do one for me a while back, welded a stock UCA mount to a 44 pumpkin, they used a high nickle rod, pre heated and controled cool down. It withstood 37" boggers for two years and is now backing up 37" Iroks. It has been beat pretty hard with no side effects.
I think it's ok to do if you have someone who knows what they are doing do the work for you.